Hydroelectric Development on Umbata Falls

Environmental Information

Environmental Screening Process

Our environmental report will be prepared to address requirements of all approving agencies including MOE Environmental Screening/Review Process, MNR Waterposer Screening and CEAA Screening.

Conceptual Design of Facility
June 2003
Submit Application Information Requirements to MNR
July 2003
Notice of Project Commencement
August 2003
Field Investigations
Aquatic and Terrestial

Consult with Public, First Nations and Agencies
to identify issues and concerns
Mail Outs
Open Houses

August-
November 2003
Undertake Detailed Studies on Outstanding Issues
May 2003 -
August 2004
Assess Potential Effects and Develop Mitigation Measures
Present Preferred Design to Public
Mail Outs
Second Round Open Houses
October 2004
Draft Environmental Report
December 2004
Agencies Review
(MNR/DFO/MOE/etc)
Notice of Completion of Report
January 2005
30 Day Public Review Period
Resolve Outstanding Issues
Finalize Report
February 2005
Submit Statement of Completion to MOE
March 2005
Project May Proceed to Other Approvals

Environmental Regulatory Requirements
A number of approvals/permits/submissions are required, including:

 
Environmental Screening/Review under the Ontario Ministry of the Environment's Environmental Screening Process for Electricity Projects
 
Project Information Package as required by Ontario Ministry of Natural Resources' Waterpower Program Guidelines
 
Environmental Screening under the Canadian Environmental Assessment Act
 
Department of Fisheries and Oceans (DFO) approval for changes to fish habitat
 
Canadian Coast Guard Approval for contruction within navigable waters
 
Ontario Ministry of Natural Resources Work Permit(s) under the Lakes and Rivers Improvement Act (approval for construction of dams, diversions, stream channelization where natural flow of river is altered)
 
Ontario Ministry of Natural Resources Waterpower Lease Agreement
 
Ontario Ministry of Environment Permit to Take Water
 
Input into White River Water Management Plan

Process Subsequent to Environmental Approval

Proceed to next section: