Environmental Information
Environmental Screening Process
Our environmental report will be prepared to address requirements
of all approving agencies including MOE Environmental Screening/Review
Process, MNR Waterposer Screening and CEAA Screening.
|
|
Conceptual Design of Facility
|
|
June 2003
|
Submit Application
Information Requirements to MNR
|
|
July 2003
|
Notice of Project
Commencement
|
|
August 2003
|
Field Investigations
Aquatic and Terrestial
|
|
Consult with
Public, First Nations and Agencies
to identify issues and concerns
 Mail Outs
 Open Houses
|
|
August-
November 2003
|
|
|
Undertake Detailed
Studies on Outstanding Issues
|
|
May 2003 -
August 2004
|
Assess Potential
Effects and Develop Mitigation Measures
|
|
|
Present Preferred
Design to Public
 Mail
Outs
 Second
Round Open
Houses
|
|
October 2004
|
Draft
Environmental Report
|
|
December 2004
|
Agencies Review
(MNR/DFO/MOE/etc)
|
|
Notice of Completion
of Report
|
|
January 2005
|
|
|
30 Day Public
Review Period
|
|
|
Resolve Outstanding
Issues
|
|
|
|
|
February 2005
|
Submit Statement
of Completion to MOE
|
|
March 2005
|
Project May
Proceed to Other Approvals
|
|
|
Environmental Regulatory Requirements
A number of approvals/permits/submissions are required, including:
|
|
Environmental
Screening/Review under the Ontario Ministry of the Environment's
Environmental Screening Process for Electricity Projects |
|
|
Project Information Package
as required by Ontario Ministry of Natural Resources' Waterpower
Program Guidelines |
|
|
Environmental Screening
under the Canadian Environmental Assessment Act |
|
|
Department of Fisheries
and Oceans (DFO) approval for changes to fish habitat |
|
|
Canadian Coast Guard Approval
for contruction within navigable waters |
|
|
Ontario Ministry of Natural
Resources Work Permit(s) under the Lakes and Rivers Improvement
Act (approval for construction of dams, diversions, stream channelization
where natural flow of river is altered) |
|
|
Ontario Ministry of Natural
Resources Waterpower Lease Agreement |
|
|
Ontario Ministry of Environment
Permit to Take Water |
|
|
Input into White River Water
Management Plan |
Process Subsequent to Environmental Approval
Proceed to next section:
Environmental
Information - Setting